Harish Sees 11,000 Lottery Signups but Just Two Open-Market Sales in Q3
Liam Engineering's Q3 report shows 11,000 applicants for subsidized Harish housing lotteries against just two open-market sales, while Bank Leumi extends credit terms.

Property market activity in Harish presents a stark contrast between heavily subsidized state housing lotteries and sluggish open-market transactions, according to recent financial filings released by Liam Engineering for the third quarter.
While approximately 11,000 applicants registered for the Ministry of Construction and Housing continuation lottery for the Target Price program at the Trapezoid Peak project, the developer sold only two open-market apartments during the quarter. Homebuyers show intense interest in securing 5-room apartments priced between 1.6 million and 1.7 million shekels through state lotteries, yet private sales remain frozen.
Sales Dynamics and Pricing Disparities
Market data reveals that regular sales pacing at the Trapezoid Peak project dropped sharply from ten contracts in the first quarter to six in the second, and just two in the third. Out of 144 total apartments distributed across four residential buildings above commercial space, 115 units are marketed under the Target Price track, leaving only 29 units for the open market. The pricing gap between the two tracks is substantial, with Target Price contracts averaging roughly 11,235 shekels per square meter excluding VAT, while open-market units averaged about 15,030 shekels per square meter overall, and contracts signed in the third quarter reached approximately 16,825 shekels per square meter. Lottery winners thus save roughly one-third compared to standard open-market prices within the same development.
To date, 82 contracts have been signed at Trapezoid Peak, reflecting a cumulative marketing rate of 57%, leaving 62 units unsold. No additional contracts have been finalized since late September, even as the underground parking structure is finished and structural framing advances. Meanwhile, Liam Engineering's secondary local development, Liam Village - Harish Maof, accelerated during the third quarter. The complex features a 63-unit residential tower, a 90-unit special housing building featuring compact units averaging 49 square meters, roughly 15,000 square meters of office space, and 9,000 square meters of commercial space. Marketing has focused initially on the small apartments, where 14 units sold during the third quarter at an average price of about 19,287 square meters, up from two units in the previous quarter, bringing total sales in that project to 22 apartments alongside three post-quarter contracts and one commercial office sale.
Financing Extensions and Corporate Expansion
Bank Leumi, which finances the Harish Maof project, granted approval in early November to postpone the deadline for meeting credit facility requirements for the project's second phase by six months, moving the target date to May 1, 2027. Additionally, the local planning committee approved an expansion of commercial spaces at Trapezoid Peak from approximately 2,500 square meters to roughly 3,500 square meters, with leasing efforts already underway.
On the financial front, Liam Engineering reported revenue totaling 25.1 million shekels for the first nine months of the year, generated entirely by the Trapezoid Peak project, marking a sharp increase from 2.1 million shekels during the same period last year. Supported by tax benefits, the company's net loss narrowed to approximately 2.8 million shekels. Beyond Harish, the firm continues to scale its urban renewal footprint, highlighted by its April acquisition of a 50% stake in a demolition-and-rebuilding project located at the Jericho Compound in Lod.