Data Center Plan Will Cost 3 Billion Shekels and Harm Health, Ministry Warns

The Ministry of Environmental Protection warns that the Electricity Authority's data center plan will increase air pollution, cost 3 billion shekels annually, and threaten public health.

Data Center Plan Will Cost 3 Billion Shekels and Harm Health, Ministry Warns
Photo: Ministry of Environmental Protection / Wikimedia Commons

The Ministry of Environmental Protection has issued a sharp warning against the Electricity Authority's plan to connect massive data centers to the national power grid, stating that the initiative will significantly increase air pollution, drive up morbidity and mortality rates, and cost the national economy roughly 3 billion shekels annually.

According to an official letter sent by Shuli Nezer, Senior Deputy Director General for Environmental Licensing and Risk Prevention at the ministry, to the head of the Electricity Authority and the Ministry of Energy, the surging electricity demand from artificial intelligence data centers will compel the accelerated depletion of Israel's natural gas reserves and force a return to outdated coal-fired power plants. Data centers are vast facilities housing servers that run complex artificial intelligence models, with a single large facility consuming as much electricity as approximately 40,000 households around the clock. The ministry estimates that by 2035, data centers could consume roughly 20% of Israel's total electricity production.

Public Health and Economic Toll

The Ministry of Environmental Protection calculates that implementing the Electricity Authority's framework will trigger a more than 10% surge in air pollutant emissions. This increase threatens to exacerbate Israel's public health crisis, where environmental and health authorities already attribute approximately 5,500 premature deaths annually to existing air pollution levels. The estimated 3 billion shekels in annual economic damage comprises 2 billion shekels from increased disease, mortality, and lost workdays, alongside more than 1 billion shekels from backup diesel generators operating near urban zones.

Furthermore, Nezer cautions that the plan will drain natural gas reserves two to three years ahead of schedule. When gas supplies dwindle, operators will face the necessity of reactivating highly polluting coal-fired units and urban generators, multiplying environmental hazards far beyond current projections.

Government Push and Environmental Pushback

The controversial proposals advance amid strong backing from the Prime Minister's Office of Israel and the National AI Directorate, which are pushing to classify data centers as critical national infrastructure via dedicated legislation. Meanwhile, the Electricity Authority has published a draft resolution proposing a quota allowing data centers to consume up to 20% of the nation's grid capacity, arguing the move will attract over 100 billion dollars in foreign investments.

Environmental organizations have sharply criticized the plan. Tomer Gertel, government relations coordinator for the Green Movement organization, asserted that Israeli citizens must not pay with their health, quality of life, and energy security for the financial gains of technology companies. The ministry demands that data centers be mandated to run on clean energy, backed by green certificates and an increased national renewable energy target of 45% by 2035.