Tel Aviv District Court Upholds 150,000 Shekel Payout for Apartment Delay
The Tel Aviv District Court ordered a construction company to pay 165,000 shekels in compensation and costs for a two-year apartment delivery delay without Form 4.

The District Court in Tel Aviv dismissed an appeal filed by a construction company, upholding a ruling that requires the developer to pay approximately 150,000 shekels in compensation to a homebuyer for a severe delivery delay. Vice President Abigail Cohen ruled that without Form 4, which authorizes building occupancy, the property could not be legally handed over, and that the compensation outlined in the purchase agreement fell below statutory requirements. The developer was additionally ordered to pay 15,000 shekels in legal costs.
The respondent purchased a three-room apartment in a TAMA 38 urban renewal project from the appellant construction company. According to the contract, the buyer was scheduled to receive her apartment in March 2019, but she actually received the keys only in January 2021, marking a delay of nearly two years. Subsequently, she filed a lawsuit against the developer for approximately 174,000 shekels, claiming breach of contract regarding the delivery deadline and failure to pay statutory compensation for the delay.
The buyer, who does not speak Hebrew, was assisted by her son in communications with the construction company. She argued that inquiries regarding the timeline for Form 4 issuance went unanswered and that she could not occupy the apartment without official approval. Conversely, the developer maintained that the apartment was ready in March 2019, but the buyer requested interior modifications that required 90 additional work days. The company claimed that contractual clauses permitted an additional 60-day extension, pushing the revised delivery date to August 2019, and alleged that the buyer withheld final payments and conditioned entry on defect repairs.
Court Rulings and Legal Standards
The Magistrate's Court partially accepted the lawsuit, acknowledging the extended delivery date of August 2019 while confirming that the apartment was handed over in January 2021. Based on an appraiser's assessment estimating fair rental value at 4,750 shekels per month, the court awarded the buyer 134,188 shekels, plus 16,000 shekels in expenses and attorney's fees.
Challenging the verdict, the construction company argued that the absence of Form 4 did not prevent occupancy and that the lower court ignored its evidence. However, Judge Cohen rejected the appeal, emphasizing that the judgment rested on solid factual findings and testimonies. She reiterated that Form 4 is mandatory for lawful delivery and constitutes a core statutory requirement that cannot be waived by contract. Consequently, because the property lacked Form 4, the delivery obligation had not matured, invalidating the developer's claim that the buyer had breached payment terms.
Furthermore, the District Court endorsed the lower court's finding that the contractual compensation of 2,700 shekels per month violated the Sale (Apartments) Law, as agreements cannot contract out of statutory protections to the buyer's detriment. With the total financial liabilities, including the latest 15,000 shekel cost order and previous litigation expenses, the developer's total payment obligation reaches approximately 165,000 shekels.