Greek Island Airport Closes For Four Months For Major Runway Expansion

Chios Island National Airport in Greece suspended commercial flights for a four-month infrastructure upgrade, closing from November 15 through March 15, 2027, for runway expansion.

Greek Island Airport Closes For Four Months For Major Runway Expansion
Photo-illustration WireIsrael: AI Generated

Travelers planning a winter getaway to the Greek islands must adjust their itineraries as the Chios Island National Airport, named after Homer, suspended commercial operations this week for a four-month infrastructure upgrade.

According to the Hellenic Civil Aviation Authority (HCAA), the airport closure spans from November 15 through March 15, 2027, to facilitate extensive runway expansion and facility modernization. The core of the project involves extending the runway northward to reach a total length of 1,799 meters. Aviation authorities note that the improvements aim to enhance operational safety and accommodate larger aircraft, ultimately bolstering the island's aerial connectivity and supporting the local economy.

Emergency Operations and Alternative Routes

While commercial flights are entirely grounded during the four-month shutdown, the Greek aviation authority confirmed that emergency helicopter operations will continue from the airport apron. These include medical evacuations, search and rescue missions, firefighting, humanitarian aid, and state flights.

Although there are no direct flights from Israel to Chios during the regular season, reaching the island during the closure requires multimodal travel. The primary route involves flying from Ben Gurion Airport to Athens, traveling to the port of Piraeus, and taking a direct ferry, which typically takes eight to nine hours, with many operating overnight. Alternatively, travelers can fly from Israel to another Greek destination with direct connections, take a short domestic flight to a nearby operating island such as Lesbos or Samos, and complete the journey via a shorter local ferry.

Accelerated Schedule for Tourism Season

Under the updated schedule, phases two and three of the construction project were shortened to four months instead of the originally planned five. The contracting firm committed to accelerating work to conclude operations by February 28, 2027, with the official reopening for scheduled traffic set for March 15, 2027.

Greek aviation officials stated that the shutdown window was selected following a thorough review of winter weather patterns and safety considerations to ensure the modernized facility reopens on time for the spring and summer 2027 tourism season. Greece has emerged as a premier destination for travelers seeking short flights and affordable getaways, though recent reports highlight rising costs across popular regions.